SwellSpot UK · Site 1
Back-to-back SwellSpot lagoons
AI concept visualisation · not a design
Confidential · Model v4.0 · 11 Sep 2026

A surf lagoon built at infrastructure cost.

Two back-to-back bays on one plot. One shared energy centre. A capital plan that retires each unproven component before the build money draws.

Both bays, ex-VAT
£2.36m
Capital to open
£2.42m
First cheque · SEIS
£250k
Y5 EBITDA · base
£660k
01 · The thesis

Demand is proven. Capital intensity is the risk.

The Wave logged about 650,000 sessions in five years, then entered administration in June 2025 over roughly £15m of build loans. Its operating business had traded. We design against that failure — not against a shortage of riders.

Evidence

Britain already buys sessions

The Wave, Coleshill and Surf London prove the category. The risk is £26–60m of concrete, not tickets.

Derived

14,100 rider-hours / £1m

Stabilised SwellSpot: 33,130 rider-hours on £2.36m. The Wave ran about 5,000 sessions a year per £1m of build.

Gate

Capital follows evidence

£250k funds the team, site, quotes and demand proof. The £1.92m build round draws only after four gates.

02 · Why this exists now

£660k on £2.42m looks cheap. Here is why it was not possible ten years ago.

Cove-class parks spent £12–60m because they copied the ocean: 15–56 acres, a destination day-trip, a large grid connection and a single construction loan. The cost point is not a secret. It is a different product.

ProjectReported capexLandRole
The Wave, Bristol£26mlarge lakeDestination · traded, then broke on loans
Surf Snowdonia£12m+quarry lakeDestination · closed
Urban Surf, Melbourne£20m+urban parkDestination
Coleshill / Stoneweg£50mdestination parkNot yet open at time of writing
Surf London, Lee Valley£60m56 acresApproved 2025, build ahead
SwellSpot UK, both bays£2.36m2–3 acresLocal club · phased

Reported figures from published coverage, not audited accounts. The comparison is capital intensity, not wave quality.

03 · The asset

Two bays, back to back, sharing one plant.

Dig both basins once. Open Bay A. Fit out Bay B from asset finance and Bay A cash after a trading gate. A weekly habit, not an annual day trip.

Twin lagoon aerial
SpecBase case
WaveAbout 4 ft · 2 ft learn setting · 50-yard ride
CycleA swell every 8.5 seconds
PlantTwo 56 kW plungers per bay
Water12,739 sq ft per bay
Throughput14 surfers / bay / hour until commissioning proves more
Plot2–3 acres · about 80 parking spaces

Bay A is lessons, families and schools. Bay B is sessions, members and evening club. Cabins sit in an optional PropCo and are not in this case.

04 · Planning and site

The largest risk is consent, not the plungers.

Gate 1 kills a plot before an option is exercised. We do not take Green Belt, flood plain or a protected landscape into Gate 3. Host leisure sites with existing consent are preferred.

ScreenPass thresholdEvidence at Gate 1
Land typeLeisure-consented host, industrial or brownfield. Flood Zone 1. No AONB, National Park or SSSI.Pre-application response
Noise and lightingPlant in a central room. Hours aligned to host. No night racing.Acoustic note + lighting plan
Highways10 min from a motorway or A-road. About 80 spaces, or shared host parking.Transport note
EnvironmentClosed-loop treatment. No discharge to a watercourse as the operating case.Drainage and water strategy
NeighboursHost already draws 250k+ visits, or a standalone plot with no sensitive frontage.Host counts or walkover
UtilitiesGas main and 250 kVA import within 500 m.Network budget offers

If pre-application fails, the option is not exercised. Tranche B never sees a refused site.

05 · Energy cost protection

The microgrid is there to protect EBITDA. Not to win an award.

Cove-class parks buy a large grid connection and then heat a lake. We buy a smaller connection, generate on site, and put waste heat into showers, sauna, clubhouse and the blanket on the bays. Gas ±30% moves project IRR by about one point. A missed DNO upgrade can move opening by a year.

Lower opex

£194k modelled energy with both bays open. Heat that would be dumped from a generator is used on site.

Smaller grid ask

CHP covers 57% of site power. The import the DNO must sell you is the remainder, plus backup.

Resilience

250 kVA battery rides through short outages so a session is not cancelled for a flicker.

Room to add solar

£245k energy centre is asset-financed. Roof and car-port PV can bolt on later without resizing the trade.

06 · Demand

Built from the ground up. Capped by the plungers.

0.8% is not a market-research slogan. It is the share of 8–54-year-olds inside a 60-minute ring that the case needs, on 2.0 visits a year. Gate 3 throws the ring away and rebuilds it on the optioned postcode, with names and deposits.

Vendor + assumption

69,020

rider-hours a year. 14 × 2 bays × 8.5 hours × 290 days. The model never prints above this cap.

Derived

114 a day

stabilised, both bays, 48% utilisation. Bay A break-even is 40 a day. Year 5 plan is 107 a day.

Assumption

13,000

paying surfers a year plus 310 members. At 1.3 visits instead of 2.0, the need rises to about 20,000 — still 1.2% of the ring.

Cross-checkFigureWhat we do with it
The Wave, five yearsAbout 650,000 sessions · 250,000 surfersDemand exists. We take 25% of its annual sessions on 9% of its build cost.
UK Surfing and Health Report, 20246.27m tried a surf sport in a year · 488,000 more regularNational pool. Not a local forecast. Used only as a ceiling.
Surfing EnglandNational governing body · clubs and membership liveSchool and club letters of intent are a Gate 3 condition.
Inland proofThe Wave was the inland location named by 96% of that surveyPeople will travel inland when the wave is reliable. We sell a weekly habit, closer to home.
Gate 3 proof, on the plot1,500 waitlist names · £200k escrowed deposits · 5 school or club LOIsThis replaces the 0.8% assumption. No names, no Tranche B.
07 · Capital and gates

Dig once. Fit out twice.

The reserve is solved, not chosen: the smallest sum that keeps cash above £50k through the downside with no new money. VAT on tickets is netted. Build is shown ex-VAT.

Uses£000
Phase 1 build — open Bay A1,685
Pre-opening, incl. fractional FD115
Transaction costs50
Working capital40
Downside reserve530
Capital to open2,420
Sources£000
SEIS Tranche A — Gate 0250
EIS + institutional Tranche B — Gate 31,920
Energy asset finance — commissioning250
Total2,420
Phase 2 Bay B — year 3, no new equity670
08 · Sequence

Four unproven components. Capital follows the sequence.

G0 · TeamFractional FD. Model and data room owned. HMRC advance assurance filed.At risk £0
G1 · SiteOption on a plot that passes the screen. Isochrone re-run on that postcode.≤ £60k
G2 · CostTwo fixed-price quotes per package. SwellSpot performance contract.≤ £150k
G3 · DemandConsent. 1,500 waitlist names. £200k escrowed deposits. Then Tranche B draws.≤ £250k
G4 · Test90-day commissioning against spec before any public sale.Tranche B
G5 · Bay BTrailing 12 months: 45%+ util, £180k+ EBITDA run-rate, 97%+ uptime.£450k finance
09 · Returns

Modest per site. Stated plainly. Stress-tested.

10-year, post-tax. Project IRR uses a 5.5× year-10 EBITDA exit. The no-exit number is shown beside it. Utilisation drives the case.

DownsideBaseUpside
Stabilised utilisationBay A 44%, no Bay BA 52% · B 44%A 60% · B 52%
Year 5 EBITDA£109k£660k£887k
Project IRR, 5.5× exit−5.7%17.4%22.8%
Project IRR, no exit−16.2%7.9%14.0%
PaybackNot within 107.2 yrs5.9 yrs
Tranche B IRR after 30% EIS−6.5%14.0%18.2%
SEIS IRR after 50% relief4.4%26.8%31.5%

Illustrative split after Tranche B: founders 25% · SEIS 18% · Tranche B 57%. Optional PropCo for cabins sits outside the EIS company.

10 · Founding team

Why Scott and Walter.

Investors back a process and a pair of people who have already lived the two halves of this asset: energy infrastructure, and the lagoon itself.

SG
Commercial · energy · delivery

Scott Graham

Founder, Surf X Group Ltd. Exclusive UK and EU SwellSpot licence. Head of New Business at Skyline DC Energy, where he built the energy division. Co-founder of CrestIQ energy monitoring. Owns the commercial path, project finance and the gated raise.

WB
Product · venue · demand

Walter Bennett

Inventor and CEO of SwellSpot. Technology partner to Surf X for about a decade. Owns the wave spec, the vendor contract and how a guest actually uses two bays. The product does not move without him.

Fractional FD · Gate 0

Owns the model, VAT, gate file and data room. Paid from Tranche A. No SEIS draw until engaged.

General manager · pre-opening

UK attractions or watersports operator. Lifeguarding and safety-management experience. Funded in the plan, not yet hired.

Investor director · Tranche B

Board seat for the lead. Related parties (licence, Skyline, CrestIQ) are disclosed and tendered.

11 · The ask

Back the process. Then the build.

Now £250k

SEIS Tranche A. Finance director, site option, pre-application, fixed-price quotes, demand proof. Stops if a gate fails.

Gate 3 £1.92m

EIS and institutional Tranche B for 57% illustrative, plus £250k energy asset finance. Opens Bay A.

Year 3–4 £0 more

Bay B from asset finance and Bay A cash once trading proves demand. No new equity.

12 · The plot

How it reads from the air.

Angled aerial of twin bays
Centre pier at dusk

Renders are AI concept visualisations. Wave size and crowding are illustrative. Geometry is confirmed by SwellSpot at Gate 2.